There's a peculiar moment in consulting when someone who didn't hire you begins assigning you additional work.
It may sound harmless: one more meeting, another deliverable, a small change. But the important question isn't simply whether you can do it. Who agreed to buy it?
When three parties have different expectations
As a subcontractor, I may be engaged by a consulting firm to perform a defined scope for its client. My agreement is with the firm that hired me, not directly with the end client.
Once delivery begins, that distinction can become blurred. An end-client manager asks for work outside the agreed scope. Perhaps the prime contractor explained the engagement differently. Perhaps assumptions were made. Perhaps circumstances changed. I don't claim to know the motivation.
I do know that a request from the end client doesn't automatically change my agreement with the contracting firm.
I've even had people offer to pay me directly for additional work. A verbal offer doesn't settle contractual authority, responsibilities, or the impact on existing commitments.
The small favors add up
Scope creep rarely arrives labeled as a major new project. It comes as a succession of requests small enough to seem unreasonable to challenge.
Every unpriced addition consumes capacity, creates expectations, and can shift risk onto someone who never agreed to accept it. The person insisting on a proper change process can end up being treated as the obstacle. I've lost relationships by enforcing those boundaries.
I don't enjoy that outcome. But accepting unauthorized obligations isn't a sound way to preserve a business relationship.
A new request isn't necessarily a no. It means bringing the contracting party into the discussion, deciding whether the work makes sense, and documenting an agreed amendment when appropriate.
Follow the agreement, not the loudest request
When commercial expectations and delivery responsibilities diverge, return to the scope and purchasing agreement. What was promised? Who can approve changes? What happens to fees, timing, and accountability when requirements expand?
This applies beyond consulting: outsourced operations, agencies, software implementations, and service providers all face the same problem when request authority and purchasing authority differ.
Scope changes aren't necessarily where profit disappears. Unmanaged scope changes are.
I am willing to discuss an amended scope when it makes sense. But the contracting party needs to be in that conversation, and the agreement has to reflect the decision.
Decide who can authorize more work
Sending additional requests back through the contracting firm sometimes cost me the relationship. I preferred that consequence to quietly accepting obligations my agreement didn't authorize. The practical question for a client or subcontractor is whether someone can say yes to extra work and also commit the resources and payment it requires. Discuss the scope decisions and handoffs affecting delivery.